By Poonam

Verified by Ajay Kumar

18 men can complete a work in 20 days. After 10 days, 6 men leave. In how many more days will the remaining men finish the work?

  1. 12 days

  2. 13 days

  3. 14 days

  4. 15 days

Answer: D

Solution

Total work=18×20=360 man-days. Work done in 10 days=18×10=180 man-days. Remaining work=180 man-days. With 12 men, required days=180/12=15.